UNDERGROUND UTILITIES

Click on a Project below to learn more about it:
2007 Billings Rehab
(Water & Sewer Line Replacement, Schedule 1)
Billings, Montana

This project consisted of open-cut sewer line replacement in alleys of the downtown Billings business district. Crews completed work on 42 new manholes, sliplining of existing sewer mains, trenchless service reconnections in alleys, extensive sewer bypass pumping, and surface restoration.
Project Owner: City of Billings
Project Amount: $1,797,000
Photo Gallery
Back to Top
South Hills Water Extension
Billings, Montana

The project is located south of Billings along Blue Creek Road and consists of 15,880 linear feet of 16" Ductile Iron Pipe, 3 Highway Bores, and one Creek Bore with 30" Casing Pipe, Booster Pump Station and 885 linear feet of 16" Insulated DIP suspended from the Tom Dolan Bridge across the Yellowstone River.
Project Owner: City of Billings, Public Utilities Department
Project Amount: $2,446,000
Photo Gallery
Back to Top
Briarwood Sewer
Billings, Montana
In 2008, COP Construction LLC was awarded the $5.2 million project for sanitary sewer improvements to the Briarwood Subdivision in Billings, Montana. This subdivision is located 5 miles south of Billings on the south side of the Yellowstone River. The scope of the work included 24,000 lineal feet of 8 inch through 18 inch sanitary sewer pipe, 850 lineal feet of suspended pipe for the crossing of the Yellowstone River from the existing highway bridge, construction of a lift station wet well, building, and related pumps and mechanical piping, installation of six bore and jack casings, and a 70 foot service bridge. The project route passed through rural property and the Briarwood Golf Course. The south end of the work ended at the small treatment plant serving the Briarwood Subdivision. The existing treatment plant was no longer needed and was removed upon completion of the project. Several areas of the sewer pipe installation required excavation depths as great as 30 feet. The bore and jack work was performed by three separate subcontractors, coupled with our support for shoring, pit construction, and ultimately assistance with grade adjustment in order to meet the requirements for the project. Work was continuous through the winter of 2008-2009 and was finished in late summer of 2009.
Project Owner: City of Billings
Project Amount: $5,257,000
Photo Gallery
Back to Top
Tree Streets Water
Rock Springs, Wyoming
This project replaced 9,500 LF of sewer, 55 manholes, 14,000 LF of water main, 27 fire hydrants, 349 services, curb, gutter, sidewalk, and 45,100 SY of asphalt pavement restoration.
Project Owner: City of Rock Springs
Project Amount: $4,723,000
Photo Gallery
Back to Top
8600 South Storm Drain
Sandy, Utah
This project consisted of construction of a new storm drain pipeline system. It included ten lateral pipelines, associated catch basins, drop structures, water quality structures, manholes and appurtenances associated with the storm drain trunk line. Also included were two precast bridges: one, 70 LF and one, 55 LF over the East Jordan and Salt Lake Canals.
Project Owner: Sandy City Corporation
Project Amount: $5,538,000
Photo Gallery
Back to Top
Springville Reach Pipeline
Springville, Utah
The Spanish Fork Provo Reservoir Canal Pipeline-Springville Reach is one portion of the overall Central Utah Water Project. This project consisted of 4.8 miles of 60" welded steel raw water pipeline installed using a slide rail shoring system. Along the length of the pipeline were 11 concrete structures of varying sizes and complexity, most with interior mechanical work. The entire pipeline was successfully tested at 450 psi. Besides the 60" pipeline, the project replaced numerous water, sewer, storm drain, and irrigation facilities. Significant traffic control included lane modifications and daily traffic switches on Highway 89, and extensive residential detours. The pipeline passed through the residential streets of Springville for about 3 miles of its total length. Extensive aging underground utilities and wet soil conditions were daily challenges. Work began in December 2009. All 25,300 LF of pipe was installed by October 2010 with the use of three mainline crews.
Project Owner: Central Utah Water Conservancy District
Project Amount: $36,097,000
Photo Gallery
Back to Top