|
COP
Projects
in Montana
|

|
|
|
2007
Billings Rehab
(Water & Sewer Line Replacement, Schedule 1)
Billings, Montana
|
|
|
|
|
|
|
This
project consisted of open-cut sewer line replacement in alleys
of the downtown Billings business district. Crews completed
work on 42 new manholes, sliplining of existing sewer mains,
trenchless service reconnections in alleys, extensive sewer
bypass pumping, and surface restoration. Project cost was $1.9
million.
Project
owner: City of Billings
|
Aronson
Road & Bridges Project
Billings, Montana
|
|

|
|
|
|
|
|
The
City of Billings awarded the Aronson Road and Bridges Project to
COP Construction LLC in January, 2008. The $5.6 million dollar project
was for the construction of two bridges and 3000 feet of new asphalt
road to provide another new access to Billings Heights from Airport
Road. Contract time required completion of all work by October,
2008. The showcase of the project involved a new bridge over Alkali
Creek. This bridge was a 200 foot single span steel girder structure,
on a curve, and with a cast in place concrete deck and walkways.
The girders required for the project weighed 630 tons and were supplied
to COP Construction LLC by Roscoe Steel, also of Billings, MT. Additional
project improvements included MSE walls, street lighting, storm
water pipe, inlets, and outfall structures, extension of the water
main, and major street landscaping.
Project
owner: City of Billings
|
|
Underwood
Water Treatment Plant Project
Billings, Montana
|
|
|
|
|
|

|
|
|
|
|
|
|
|
|
|
|
|
|
|
In
1915 the City of Billings purchased its waterworks from Montana
Water Company at a cost of $315,000. The original waterworks plant
was built in 1886-87, and at that time, the City had a population
of approximately one thousand.
Since then the City of Billings Water Treatment Facility (aka Gerald
D. Underwood Water Treatment Plant) has continued to expand in an
ongoing effort to keep up with the growth of Billings. The source
of supply for the City's waterworks is the Yellowstone River. The
nominal capacity of the water treatment plant is about 50 million
gallons per day (MGD). Daily average usage is approximately 24 MGD,
however at peak times during the summer months the plant will process
at capacity-50MGD.
Water is pumped from the plant to eleven different zones within
the City, and a 600-foot elevation differential exists between the
highest and lowest portions of the City's water service area. The
plant currently services approximately 115,000 people.
Current
Expansion
In 2005 the City of Billings contracted with COP Construction LLC,
a prominent, local, municipal general contractor to both renovate
and expand the Underwood facility. This is a very technically challenging
project in many respects, especially in light of the fact that this
is a renovation/expansion around an ongoing operation. The completed
project is estimated at $17 million and will take about two years
to complete. When completed, the treatment plant's capacity will
increase about 20% or to a capacity of 60MGD. This should serve
the City's population well into the future.
|
|
Pablo
Dam - Stage II Modification (SOD)
Near Pablo, Montana
|
|
|
|
|

|
|
|
The
Pablo Dam-Stage II project encompassed completely draining the Pablo
Reservoir, excavation, de-watering, removal and replacement of inlet
and outlet works, material processing and zoned backfilling. The
project's purpose was to improve dam safety and update irrigation
and stock watering for irrigation members. This project is located
near Pablo, Montana on the Confederated Salish and Kootenai Reservation.
Crew
size: 20-60 (including subcontractors)
Project
Owner: The Confederated Salish and Kootenai Tribes
Contract
Administrator: Bureau of Reclamation
|
|
|
Laurel
Intake Structure
Laurel, Montana
|
|

|

|
|
This
job consists of 3 significantly different activities: the Intake
Structure, Pump Station, and Intake Pipe System. The Intake is a
poured-in-place concrete structure in the Yellowstone River that
will be below water. The Intake is approximately 40 feet long and
12 feet high. The pipe from the Intake to the Pump Station consists
of approximately 700 feet of 24" dictile iron pipe. The Pump
Station is 3 stories high with 2 stories below ground. The Pump
Station also includes 7 pumps and related intake piping and controls.
Each pump is capable of pumping 2000 gallons per minute.
Crew
size: 15
Project
owner: City of Laurel
|
|
South
Hills Water Extension
Billings, Montana
|
|
|
|
|
|
The project is located south of Billings along Blue Creek Road and
consists of 15,880 linear feet of 16" Ductile Iron Pipe, 3 Highway
Bores, and one Creek Bore with 30" Casing Pipe, Booster Pump
Station and 885 linear feet of 16" Insulated DIP suspended from
the Tom Dolan Bridge across the Yellowstone River.
Crew
size: 15
Project
owner: City of Billings, Public Utilities Department
|
| |
|
|
Briarwood Sewer Main Extension
Billings, Montana
|
|

|

|
|

|

|
|

|

|
|

|

|
|

|

|
|

|

|
|

|
|
In 2008, COP Construction LLC was awarded the $5.2 million project for sanitary sewer improvements to the
Briarwood Subdivision in Billings, Montana. This subdivision is located 5 miles south of Billings on the
south side of the Yellowstone River. The scope of the work included 24,000 lineal feet of 8 inch through
18 inch sanitary sewer pipe, 850 lineal feet of suspended pipe for the crossing of the Yellowstone River
from the existing highway bridge, construction of a lift station wet well, building, and related pumps
and mechanical piping, installation of six bore and jack casings, and a 70 foot service bridge. The project
route passed through rural property and the Briarwood Golf Course. The south end of the work ended at
the small treatment plant serving the Briarwood Subdivision. The existing treatment plant was no longer
needed and was removed upon completion of the project. Several areas of the sewer pipe installation
required excavation depths as great as 30 feet. The bore and jack work was performed by three separate
subcontractors, coupled with our support for shoring, pit construction, and ultimately assistance with
grade adjustment in order to meet the requirements for the project. Work was continuous through the
winter of 2008-2009 and was finished in late summer of 2009.
Project
owner: City of Billings
|
|
Highway 191 - Gallatin Canyon
Big Sky, Montana
|
|

|

|
|

|

|
|

|

|
|

|

|
|
The Highway 191
- Gallatin Canyon Project was a $12.8 million dollar project for the Montana Department of Transportation that began in June 2008 and consisted of improvements that enhanced public safety at Big Sky, Big Sky Spur, Jack Smith Bridge Area, Swan Creek Campground Area and the Spanish Creek Area. It began on Highway 191 at the mouth of the Gallatin Canyon to Big Sky, a total of 15 miles. Improvements included replacing two bridges – the Big Sky Bridge and the Swan Creek Bridge; widening road shoulders; improving site distance for drivers; installing new and upgraded guardrails; and adding right and left turn lanes of Highway 64 going to Big Sky.
Project
owner: Montana Department of Transportation
|
|